Early Delivery for National Distribution Centre

Posted by admin on August 11, 2016


Following on from June's Insight on Teccon's progress on the first of 3 national distribution warehouses here's an update and photos of the completed South East distribution centre, delivered 2 weeks early.

What we delivered

The Distribution Centre now houses 750 bays of industrial shelving on a single tier mezzanine floor over multiple docking stations. The installation was successfully delivered without effecting operations during installation.

The project, through close and open communication with the client, demonstrated our teams precise planning and execution, from consultation through to installation, on time and on budget.

Industrial Shelving


What it means for them

In line with their expansion plans, the completion of the South East Distribution Centre allows the customer to hold a greater range of stock and open new lines.


What next?

Work has already begun on the Midlands Distribution Centre spread over 2 warehouses, consisting of a further 2250 sq metres on a two tier mezzanine floor, over 2000 bays of industrial shelving, 300 bays of pallet racking and alterations to a 8000 bay pallet racking system.

We'll be updating Insight with it’s progress and photos next week.